Projects
We carry out projects of any complexity for the benefit of Man
-
4000+projects
-
1.3 billion ₽annual investment in development
Construction of crossings using trenchless technologies
Krasnoyarsk region
2018-2022
Customer: JSC "Suzun"
Arrangement
Transitions made - 9
Total length - 4 312 m
Pipe diameter -1020 mm
The construction was carried out beyond the Arctic Circle in the permafrost zone, in a poorly developed area with a lack of permanent transport communications and communications.
YaNAO
2020
Customer: JSC "Messoyakhaneftegaz"
Arrangement
Transitions made - 1
Total length - 900 m
Pipe diameter - 820 mm
The world's northernmost directional drilling crossing.
The company SP VIS-MOS" LLC has set a world record in construction by the method of directional drilling (HDD). In the Arctic, the construction of the northernmost not only in Russia, but also in the world, underwater crossing of the oil pipeline across the Messoyakha River on the Gydan Peninsula in the Yamalo-Nenets Autonomous Okrug was completed using horizontal directional drilling technology. "
Yamalo-Nenets Autonomous Okrug
2019-2020
Customer: LLC "Kharampurneftegaz"
Arrangement
Transitions made - 4
Total length - 3713 m
Pipe diameter -1220 mm
The work was carried out in particularly unfavorable geological conditions, which make the work as difficult as possible due to the predominance of permafrost soils.
YaNAO
2018-2019
Customer: Novatek-Tarkosaleneftegaz LLC
Arrangement
Transitions made - 13
Total length - 8 659 m
Pipe diameter -1220 mm, 820 mm, 530 mm
Work on the construction of crossings on the territory of the Severo-Russkoye field was carried out in the zone of permafrost soils of a heterogeneous structure, which required the use of modern navigation equipment, which makes it possible to maintain the well drilling trajectory with maximum accuracy. And the crossing over the Taz River with a diameter of 1220 mm and a length of 2048 m is an unprecedented success object made with such characteristics.The weight of the pipeline structure at the time of pulling through was 2633 tons.
Krasnodar region
2015
Customer: OOO "Gazprom invest"
South European Main Gas Pipeline
Transitions made - 2
Total length - 1708 m
Pipe diameter -1420 mm
SP VIS-MOS LLC completed a set of works on the arrangement of underwater crossings across the Zhuravka and Beisug rivers at the facility "Expansion of the UGSS to ensure gas supply to the South Stream gas pipeline. Stage 2 (eastern corridor), to ensure gas supply in the volume up to 63 billion m3/year". South European gas pipeline. Pochinki - Anapa section, km 1379-km 1570.5.2"
Saint Petersburg
2014-2015
Customer: LLC "Petrokom"
Construction of a water conduit
Transitions made - 2
Total length - 350 m
Pipe diameter - 1000 mm
In the construction of the water supply system to the Western part of Vasilyevsky Island in St. Petersburg, one press-screw unit and two horizontal directional drilling units were involved. To locate drilling complexes on sites in the channel part of the Neva River near Petrovskaya and Arsenalnaya specialists of SP VIS-MOS LLC, two temporary artificial platforms were built to carry the main load.
Krasnoyarsk region
2013-2014
Customer: JSC "Sibnefteprovod"
Main oil pipeline
Transitions made - 3
Total length - 2967 m
Pipe diameter -1220 mm, 273 mm
The construction of crossings across the Taz River has become one of the most technically complex facilities of the Zapolyarye-Purpe oil pipeline system. start drilling operations before the opening of transport links arranged by winter roads Drilling operations were carried out in permafrost soil, in the conditions of the Arctic, at extremely low temperatures.
KhMAO, YaNAO
2012
Customer: Zapsibtransgaz LLC
Completed transitions - 14
Total length - 6500 m
Pipe diameter - 820 mm, 530 mm
The construction of crossings was carried out in a short time using 6 drilling rigs simultaneously.
Yamalo-Nenets Autonomous Okrug
2011-2012
Customer: CJSC "Vankorneft"
Completed transitions - 8
Total length - 7043 m
Pipe diameter - 1220 mm, 820 mm
Drilling operations were carried out in permafrost with high abrasive properties. A drilling tool with special rock-breaking equipment was used for driving. Of particular difficulty was the preparatory period, due to the remoteness of the objects and the need to work in completely autonomous conditions.
Sakhalin-Khabarovsk-Vladivostok
2010-2011
Customer: LLC "Gazprom gas distribution"
Gas transportation system
Transitions made - 2
Total length - 2857m
Pipe diameter - 426 mm
Super-long crossing. The construction was carried out by two drilling rigs by docking oncoming pilot wells from opposite banks of the obstacle (Russky Island - Nazimov Cape). During the construction process, a modern navigation system was used that allows the wells to see" each other and ensures high docking accuracy. The strength of the overcome soil reached 174 MPa, which is comparable to the strength of metal and required the purchase of a specialized drilling tool from an Australian manufacturer.
Krasnodar region
2009-2010
Customer: LLC "Piter Gaz"
Gasification of Olympic venues
Completed crossings - 5
Total length - 4256 m
Pipe diameter - 762 mm, 325 mm
The work was carried out in cramped conditions of mountainous terrain, on minimal sites, with a large elevation difference, in heavy-duty rocky soils. A particular problem was rock fissuring, local faults, interlayering of rocky and non-cohesive soils. This project involved laying a linear part of the pipeline in the Black Sea , and the connection sections were carried out using the horizontal directional drilling method with an exit point to the sea.
Leningrad region
2007-2008
Customer: CJSC "Yamalgazinvest"
International project Russia-Germany gas pipeline
Transitions made - 2
Total length - 1835 m
Pipe diameter - 1420 mm
The construction of crossings was carried out in conditions of complex geology, in sandy gravel soil with a high percentage of large boulders. To pass the route, a special rock-cutting drilling tool developed by engineers of SP VIS-MOS LLC was used.
Vologda, Tver, Yaroslavl regions
2004
Customer: OAO "Baltnefteprovod"
The system of main oil pipelines
Transitions made - 3
Total length - 1607 m
Pipe diameter - 1020 mm
The construction of the crossing under the Uleima River took place in extremely difficult boulder soil, the diameter of the boulders exceeded two meters, which greatly hampered the development of the well. For successful construction, a drilling tool with reinforced rock-breaking elements was manufactured at the production base of LLC SP VIS-MOS.
Krasnodar region
2000-2002
Customer: JSC "Stroytransgaz"
International project Russia-Türkiye gas pipeline
Transitions made - 8
Total length - 6080m
Pipe diameter - 1420 mm
To overcome difficult areas, a unified drilling tool was manufactured at the production base of SP VIS-MOS LLC. To stabilize the well, drilling fluid was selected directly at the construction sites in a mobile laboratory.
Exploration and production drilling
Deposits Lora and Talnikovaya Olsky district of the Magadan region
2021-2022
Customer: OOO "Nedra M", OOO "MC "Far East"
More than 10,000 linear meters have been drilled and cored.
Core drilling is one of the most productive and economical methods of mine workings. Core core drilling allows determining the depth of the rock with the highest accuracy. When drilling, a point effect on the soil along the radius of rotation occurs, a solid mass of rocks is drilled out without disturbing their structure and condition, which makes it possible to carry out a comprehensive analysis of the studied breed.
Yakutia
2019-2022
Customer: JSC "Alrosa"
Drilling operations with core sampling and a complex of geophysical surveys during exploration and deep horizons of the Udachnaya pipe
Wells at the Vostochny" ore body - total penetration of 14,200 m
Wells in the "Western" ore body - total penetration of 21,000 m
Wells at the Udachny mine - 1700 m
Yakutia
2017-2019
Customer: JSC "Alrosa"
Drilling operations with a complex of geophysical surveys in the exploration of deep horizons of the Yubileinaya pipe
Well No. 438, total penetration - 727 8 m.;
Well No. 439, total penetration - 6672 m.
A total of 20 fan exploration shafts were drilled.
Tula region, Novomoskovsk rock salt deposit
since 2017
Customer: SC "MHK "EuroChem"
Built - 4 brine wells
The construction of large-diameter wells is in demand by the mining industry for the purpose of degassing and utilizing gases from mines, supplying air to existing mine workings (shafts, adits), as well as for the extraction of minerals that cannot be mined in an open way.
LLC "SP VIS-MOS" has experience in the construction of these wells in difficult geological conditions, including the use of a unique specialized tool.
Ulyanovsk, Samara, Amur regions and the Republic of Tatarstan
2016-2022
Customer: NK "Action", JSC "Zarubezhneft", LLC "MNKT", LLC "Gapromgeologorazvedka"
A full range of works on the construction of production, exploration, prospecting and appraisal wells on a turnkey basis has been completed. Our team of specialists has extensive experience in solving complex problems in different climatic conditions, a high level of qualification, and has an extensive knowledge base and database, which allows put objects into operation within the contractual terms and in compliance with the financial interests of the Customer.
Republic of Komi, Republic of Tatarstan, Samara and Sakhalin regions
2013-2022
Customer: Lukoil Komi LLC, Tatneft PJSC, Rosneft Oil Company, Samaraneftegaz JSC, NNK-Sakhalinmorneftegaz LLC
Built - 170 production and steam injection wells.
The production of heavy oil and bitumen is complicated by their high viscosity, the need to use energy-saving methods of deep mining. The SAGD technology (from the English. Steam Assisted Gravity Drainage - thermogravitational drainage of the reservoir) used by the company SP VIS-MOS" allows you to "warm up" the reservoir and faster, easier to extract the fluid, is innovative and highly cost-effective
Construction of linear facilities
Ulyanovsk
2023
Customer: UMUP "Ulyanovskvodokanal"
Overhaul of the centralized water disposal system in Krotovka settlement, Ulyanovsk region.
Krasnodar region
2022
Customer: Chernomortransneft LLC
Reconstruction of a section of the main oil pipeline "Tikhoretsk-Tuapse-2".
KhMAO
2021-2022
Customer: JSC "Transneft-Siberia"
Reconstruction of the section of the main oil pipeline "Nizhnevartovsk-Kurgan-Kuibyshev" 217 km - 284 km.
KhMAO
2021-2022
Customer: JSC "Transneft-Siberia"
Reconstruction of the section of the main oil pipeline "Surgut-Polotsk" 342 km - 380 km.
KhMAO
2021-2022
Customer: JSC "SiburTyumenGaz"
Reconstruction of the main product pipeline "Gubkinsky GPP-Yuzhno-Balyksky GPP".
Construction of an additional reserve line 22 km, incl. 10 km in wetlands
KhMAO
2020-2022
Customer: RN-Yuganskneftegaz, OOO
Construction of oil pipelines, construction of oil and gas gathering networks at the fields: Ust-Balykskoye, Solkinskoye, Priobskoye, Yuzhno-Surgutskoye, Vostochno-Pravdinskoye. The total length is over 100 km.
Krasnoyarsk region
2018
Customer: SUZUN JSC
Construction of infield pipelines.
KhMAO
2017
Customer: Gazpromneft-Khantos, OOO
Arrangement of the Maloyugansky site for trial operation. Construction of a pipeline for the oil and gas gathering of the Maloyugansky field.
Krasnoyarsk region
2015
Customer: SUZUN JSC
Construction of an interfield oil pipeline OPF of the Suzunskoye field - CPS of the Vankor field
Arrangement of well pads at oil and gas fields
KhMAO
2020-2022
Customer: PJSC "Rosneft"
- Manufacturing and installation of metal structures (stairs, platforms, sheds, beams, cable racks, floodlight matches, metal heads)
- Installation of start-up and reception chambers, drainage tanks with piping
- Installation of cable lines and communication networks
- Installation of control and automation devices, fire and security alarms
- Piping of oil wells with output through the metering unit to the main oil pipeline
- Protection of oil and gas equipment and pipelines from corrosion
- Improvement of the territory and access roads
Site preparation of well pads and access roads
KhMAO
2020-2022
Customer: PJSC "Rosneft"
The total volume of dumping is 5,500,000 cubic meters
- Clearing the area
- Backfilling of the base of the well pad or flare system site using soil, sand and crushed stone and compaction
- Installation of shut-off valves and bunding along the perimeter of the bush, culverts
- Construction and arrangement of sludge pits with impervious screen
- Road construction / roadways, infield roads, winter roads