Our building site on the Sakhalin island.

In less than six months, two drilling complexes under the leadership of Sergey Botov and Alexander Mukhortov completed the reconstruction of four oil wells at the Kydylanya field.

Sidetracks were drilled to a total depth of 7,450 meters. The weather on Sakhalin this year is especially treacherous: low temperatures down to -43 and strong gusts of wind. But, despite all the difficulties, the ZJ-40 mobile drilling rig was moved and installed at the next well No. 170. After the completion of commissioning work, the process of restoring the next oil source will begin.