The route of the main product pipeline is at the final stage

The main product pipeline route, running from the Nizhnevartovsk Gas Processing Plant (GPP) to the junction point with the 660th kilometer of the reconstructed Gubkinsky GPP - Yuzhno-Balyk GPP product pipeline, is at its final stage.

Today, SP VIS-MOS LLC is completing the construction of the second 1669 meter long crossing across the channel of the Siberian Ob River MEGA. Two pipeline threads have been laid - the main and reserve. A well has been drilled and today the main thread is already laid in a “case” parallel to the reserve one.

The head of the drilling complex, Mikhail Kabanov, notes well-coordinated work of the team under the leadership of drilling foreman Sergey Saushkin on the horizontal directional drilling rigs NK-250 and PD 450/150.