The "SP VIS-MOS" LLC is doing the gasification project of the Kostroma region.

The "SP VIS-MOS" LLC is doing the gasification project of the Kostroma region.

Construction of the first of five underwater pipeline crossings 1140 meters long and a 530 mm in diameter was successfully completed by the horizontal directional drilling method.

Taking into account special features of soils, special protective coating - 30 mm thick layer of concrete on the surface of a pipe - was applied to protect insulation of the pipeline from damage during pulling through process. Construction of four crossings 1140 - 1540 meters long to be done.

We thank the drilling crew led by Stanislav Ivanyukov and keep our fingers crossed for new successes!